9/6-Delivery of Lighting Fixtures and Supplies to Be Stored in Big Gym Foyer
9/10-Work Will Start-Gym Completely Closed
Lighting Project will take approximately 1 month
This will be followed by the scoreboard replacement project which will take approximately 1 month (restricted access will be allowed in the gym during this time)